Wersja oficjalna awarii :
At approximately 4:15AM CST, a pair of redundant Powerware 500KVA UPS units failed creating a power failure in section B of our DLLSTX2 datacenter. Emergency teams were deployed within minutes and power was restored within minutes but intermmittment power outages did occur until 6:45AM CST. Powerware, JT Packard, and electricians are currently onsite with over 100 Planet technicians working to resolve the issue. We do not anticipate any further outages . A formal RFO will be released once the team debriefs. We apologize for all issues that has caused.